Today they arrived a bit later, since they had to pick up some sand.
The first truck load arrived at 09:00 in the morning, and we got 4 trucks full.
The sand and pebbles were let go on to the floor bed they had built.
It was then even-out and a seam put in the middle.
The seam is there because the floor is bigger than 35m2, and they are afraid that the floor might sag with weight, so it's going to be two slabs of concrete.
Now, the wait is for the weather. They want 48 hours of dry weather.